Most of the windows are now installed in plots 3 and 4.
A COSY CONSTRUCTION SITE
There's still a lot of equipment and building materials on site. It can therefore be quite a challenge to move around.
Plot 1 block & beam and steel bases have been installed. Plot 2 steels and brickwork are now complete. Plots 3 & 4 brickwork and roof are both complete.
First fix plumbing and electrical have been completed and plasterboard is almost complete. The scaffolding has been removed and lower level roofs have been completed. Lower floor walls have been mist coated and kitchen fitting has started.